Delivering expertise across 18 university buildings

checkmate-fire-acc-cs-1.webp

1 August 2026

Working sensitively around listed and heritage buildings, we carefully sequenced works around academic calendars, maintaining fire safety while minimising disruption to students and operations.

Reading time:

We are one of four appointed framework contractors delivering fire door remediation, replacement and associated passive fire protection works across the University of Leeds student accommodation building.

Works are delivered under a structured annual programme aligned to academic calendars, capital planning cycles and estate-wide fire strategy objectives. Springfield Mount formed part of our Year 1 allocation and was identified as one of the most technically challenging properties due to its Victorian construction and historic alterations.

Scope and scale of work

Across our allocated buildings the scope includes:

  • Installation of new compliant FD30 and FD60 fire doorsets

  • Remediation of existing fire doors where technically viable

  • Validation surveys to confirm accurate scope and fire line integrity

  • Associated compartmentation works

To date we have delivered:

  • 750+ fire door replacements

  • 600+ fire door remediations

  • Works across 18 blocks and multiple academic buildings

  • Delivery within listed and heritage properties

Delivery in a live occupied building

Delivery requires:

  • Building-by-building and floor-by-floor sequencing

  • Daily liaison with the University Fire Officer

  • Coordination with Accommodation Teams

  • Strict protection of escape routes

  • Noise and access controls

Works are typically scheduled around defined academic windows, including summer recess, to minimise disruption to teaching and assessment activities.

No fire door is left incomplete at the end of any working day, ensuring compartmentation integrity is maintained at all times.

Key challenges and controls.

Estate diversity and heritage sensitivity

The University estate includes listed heritage properties with varying wall types, structural arrangements and legacy alterations.

We undertake detailed validation surveys prior to works commencement, confirming door ratings, substrate compatibility and fire line continuity before issuing lump sum pricing. Early technical engagement ensures installation details align with manufacturer certification, BS 8214 and the University’s fire strategy.

Where required, door finishes and architraves are carefully matched to preserve heritage aesthetics while achieving full compliance.

Compressed academic delivery windows

Programme delivery must align with immovable academic deadlines and building availability.

We implement critical path programming, structured sequencing and daily progress monitoring to ensure completion within agreed timeframes. Contingency allowances are built into programmes to manage unforeseen findings during intrusive works without jeopardising completion.

Quality assurance and compliance

  • External quality and health & safety audits undertaken every two weeks

  • 100% audit scores achieved

  • Handover completed with zero snagging

  • Full digital QA records provided

  • Regulation 38 documentation issued promptly

  • Transparent lump sum pricing provided following validation surveys

No enforcement notices, reportable incidents or programme overruns have occurred across the framework term to date.

Outcomes

  • 100% of allocated works completed ahead of agreed programme

  • Zero snags at final handover

  • Achieved 100% external audit scores

  • Recognised by client as highest performing framework contractor

  • Awarded increased scope within subsequent annual programmes

In recognition of the quality and technical excellence demonstrated at Springfield Mount, the project was awarded the ASFP Installation/Project of the Year 2025 (Under £1m category). This independent industry award validates the compliance, workmanship and delivery standards achieved.

Just a quick email to say thanks for turning the Springfield Mount project around and getting it over the finish line in good time. The Residences staff were happy with the quality of the works and how clean the site was.

Myself and RLB, who undertook the quality monitoring side of things, were also happy with the results and we found communications were excellent throughout the project.

Please pass my thanks onto James and Michael and the rest of your team and I look forward to working with you again next year.


Shaun Solari, Project Manager, University of Leeds

Managing fire safety across multiple student accommodation buildings?